MDA Multan Extend Deadline for Development in Fatima Jinnah Town Phase-I

MDA Multan Extend Deadline for Development in Fatima Jinnah Town Phase-I

Development work will complete in December 2013 – Nazir & Company Ltd

Nazir & Company is contractor of FJ Town Phase I

Multan (Saturday, July 27, 2013) – Project Director Nazir and Company Pvt. Ltd. Mr. Muhammad Sarwar Faiq has said 75% development work in Fatima Jinnah Housing Scheme Phase-I Multan has been completed.

Fatima Jinnah Town Multan Phase-I Development Status (Published in Daily Nawaiwaqt Multan dated 27-7-2013)

Fatima Jinnah Town Multan Phase-I Development Status (Published in Daily Nawaiwaqt Multan dated 27-7-2013)

Project director thanks Multan Development Authority (MDA) governing body for extending development completion date till the December 31, 2013 (end of current year).

Mr, Faiq said that Road earth work, Sewerage, carpeting, boundary wall, Pump house and tube-well bore operator quarters work has been completed. other development will complete in time.

He hope hope that housing colony will be ready for construction of houses for allottees as per promise.